19 November 2012
ORCHID©: A historic commissioning!

November 14th 2012 around 7.30 pm, the ORCHID© module has generated its first kWh.

Adjustments are ongoing but the first ORC pilot plant and the proprietary designed turbine have proven the reliability of their technical design and engineering.