10 July 2017
Enertime successfully delivers the 1.6 MWe ORC module within the premises of its subcontractor at Le Creusot

In 2016, Enertime received an order financed by the European Bank for Reconstruction and Development (EBRD) for the design, manufacture and commissioning of an ORC biomass cogeneration module to be installed in The city of Kamyanets-Podilskyi in western Ukraine.

The commissioning of the 1.6 MWe ORC module by the Ukrainian customer was successfully completed on July 4th at the premises of the ENERTIME subcontractor at Creusot and in charge of the assembly. Marine Chambon, Enertime biomass project engineer at Enertime, says: "The module is now being dismantled and packaged for a scheduled departure at the end of July in the direction of Kamyanets-Podilskyi in the west of Ukraine, where it will be integrated with the rest of the facility, namely a biomass cogeneration plant ".